Facility: SPP "Fotone Energy Pogorodnoye", 15 MW
The works were performed for 5.7 MW
Address: Podgorodnoye, Dnipropetrovsk Oblast
Customer: ООО "EDS-ENGINEERING"
Duration of construction works: July - August 2018
The following works were performed:
- Design of metal structures for the installation of photovoltaic modules
- Supply of metal structures to the facility.
- Geodetic breakdown of the site.
- Drilling wells for support stands - 6832 wells.
- Assembly and installation of metal structures in the design position - 488 pieces.
- The construction of the foundations for complete transformer substations - 6 pieces.
- Installation of a security fence of a site of a solar power station.
The number of staff at the facility: 35 specialists.
Special machinery:
- 2 JCB 4cx backhoe loaders;
- 1 wheel mini-loader JCB 155;