On January 8, 2024, the BSG team began the reconstruction of a grocery store for our regular customer - "ATB-Market". Although the premises do not look very aesthetically pleasing now, in a few months we will turn it into a modern supermarket. We plan to finish the work by April 25, 2024. By this time, BSG specialists had already completed:
- preparatory work with walls,
- laying partitions,
- installation of plasterboard partitions,
- preparation of openings for doors and windows.
We plan to carry out the following types of work during the entire renovation of the store:
- general construction, plumbing and electrical works;
- heating and ventilation works and commissioning;
- arrangement of fire cabinets;
- formation of metal and fire doors;
- installation and commissioning of cargo lifting equipment and passenger elevator;
- installation and commissioning of refrigerating chambers and automatic fire alarm and smoke removal;
- installation of stained glass systems and commissioning of automatic sliding doors;
- installation of advertising media.
We believe that we have had a good and active start to the year, considering the volume of work that we have to complete. Although during the war, the Ukrainian economy passes a difficult test of strength, we all hold together, do not lose momentum and continue to work so that Ukraine can withstand all the burdens, endure and win.