Facility: SPP "Shyroke Solar Park", 12.55 MW
Duration of construction works: 85 calendar days (including work in winter)
The following works were performed:
- Design of metal structures for the installation of photovoltaic modules
- Geodetic breakdown of the site, supporting structures
- Drilling wells for support stands - 14854 wells.
- Assembly and installation of metal structures in the design position - 1061 pieces.
The number of staff at the facility: 40 specialists.
Special machinery was involved:
- 1 JCB 4cx backhoe loader;
- 1 wheel mini-loader JCB 155;
- 1 tractor for distribution of supporting metal structures for photovoltaic panels.