+38 (073)-366-10-80 +38 (056)-722-20-79 bsg.office.dp@gmail.com

Facility: SPP "Shyroke Solar Park", 12.55 MW

Duration of construction works: 85 calendar days (including work in winter)

The following works were performed:

  • Design of metal structures for the installation of photovoltaic modules
  • Geodetic breakdown of the site, supporting structures
  • Drilling wells for support stands - 14854 wells.
  • Assembly and installation of metal structures in the design position - 1061 pieces.

The number of staff at the facility: 40 specialists.

Special machinery was involved: 

  • 1 JCB 4cx backhoe loader;
  • 1 wheel mini-loader JCB 155;
  • 1 tractor for distribution of supporting metal structures for photovoltaic panels.

 