Facility: SPP "Malaya Belozerka" 22.9 MW
Duration of construction works: 95 calendar days (including work in winter)
The following works were performed:
- Design of metal structures for the installation of photovoltaic modules
- Geodetic breakdown of the site, supporting structures
- Drilling wells for support stands - 27300 wells.
- Assembly and installation of metal structures in the design position - 1950 pieces.
- Installation of a security fence of a site of a solar power station.
The number of staff at the facility: 55 specialists.
Special machinery was involved:
- 3 JCB 4cx backhoe loaders;
- 1 wheel mini-loader JCB 155;
- 2 tractors for distribution of supporting metal structures for photovoltaic panels.