Facility: SPP "Malaya Belozerka" 22.9 MW

Duration of construction works: 95 calendar days (including work in winter)

The following works were performed:

  • Design of metal structures for the installation of photovoltaic modules
  • Geodetic breakdown of the site, supporting structures
  • Drilling wells for support stands - 27300 wells.
  • Assembly and installation of metal structures in the design position - 1950 pieces.
  • Installation of a security fence of a site of a solar power station.

The number of staff at the facility: 55 specialists.

Special machinery was involved: 

  • 3 JCB 4cx backhoe loaders;
  • 1 wheel mini-loader JCB 155;
  • 2 tractors for distribution of supporting metal structures for photovoltaic panels.