Facility: SPP «Makov-1», 9.9 MW
Customer: ООО "EDS-ENGINEERING"
Duration of construction works: August - October 2018.
The following works were performed:
- Design of metal structures for the installation of photovoltaic modules
- Supply of metal structures to the facility.
- Geodetic breakdown of the site.
- Drilling wells for support stands - 14528 wells.
- Assembly and installation of metal structures in the design position - 908 pieces.
- The construction of the foundations for complete transformer substations - 6 pieces.
- Installation of a security fence of a site of a solar power station.
The number of employees at the facility: 40 specialists.
Special machinery:
- 2 JCB 4cx backhoe loaders;
- 1 wheel mini-loader JCB 155;
- 1 tractor for distribution of supporting metal structures for photovoltaic panels.