Facility: SPP «Makov-1», 9.9 MW

Customer: ООО "EDS-ENGINEERING"

Duration of construction works: August - October 2018.

The following works were performed:

  • Design of metal structures for the installation of photovoltaic modules
  • Supply of metal structures to the facility.
  • Geodetic breakdown of the site.
  • Drilling wells for support stands - 14528 wells.
  • Assembly and installation of metal structures in the design position - 908 pieces.
  • The construction of the foundations for complete transformer substations - 6 pieces.
  • Installation of a security fence of a site of a solar power station.

The number of employees at the facility: 40 specialists.

Special machinery:

  • 2 JCB 4cx backhoe loaders;
  • 1 wheel mini-loader JCB 155;
  • 1 tractor for distribution of supporting metal structures for photovoltaic panels.