The company "BuildService Group" completed the construction and installation works at the SPP "Makov-1" with the capacity of 9,9 MW in Khmelnytskyi Oblast.
The general contractor was ООО "EDS-ENGINEERING" Works on an area of 20 hectares were performed for a little more than two months - from August to November 2018.
For 70 days, our company performed a geodetic breakdown of the site, drilled 14528 wells for the support stands of the metal structures, assembled and installed in the design position 488 metal structures for the installation photovoltaic, constructed foundations for 6 transformer substations -10/0.4 kV and a distribution point RP 10 kV, and also installed the fencing section of the solar power station.
The project "Makov-1" is the largest in the field of solar energy, which the company "BuildService Group" has currently performed. The whole volume of work was performed by 40 of our specialists with the involvement of 4 units of special machinery, including 2 JCB 4cx backhoe loaders, a JCB 155 mini loader, and a tractor for distribution of supporting metal structures for photovoltaic panels..