The company "BuildService Group" completed the construction and installation works at the SPP "PHOTON ENERGY" with a capacity of 15 MW in Podgorodnoye Dnipropetrovsk Oblast
We were entrusted with the work for 5.7 MW of the total planned capacity of 15 MW. The implementation of this ambitious project took a month and a half, work was performed from July to August 2018. The general contractor was ООО «EDS-ENGINEERING»
For 45 days, our specialists performed a geodetic breakdown of the site, drilled 6,832 wells for the support stands of the metal structures, assembled and installed in the design position 488 metal structures for the installation photovoltaic modules (total capacity 5.7 MW), and also made the installation of the fencing for the site of SPP.
It should be noted that the entire volume of work was performed by 35 of our specialists with the involvement of 3 units of special machinery, including 2 JCB 4cx backhoe loaders and a JCB 155 mini loader.