The company "BuildService Group" completed the construction and installation works at the SPP "Sun Energy" with a capacity of 2 MW in Podgorodnoye Dnipropetrovsk Oblast

 The implementation of this project took 40 days: from June to August 2017. The general contractor was ООО "EDS-ENGINEERING".

 Our specialists performed a geodetic breakdown of the site of the future SPP (area of 4.86 hectares), drilled 3200 wells for the support stands of the metal structures, assembled and installed in the design position 400 metal structures for the installation photovoltaic modules. The installation of a security fence of a site of a solar power station was also performed.

 The following works were performed:

  • Design of metal structures for the installation of photovoltaic modules.
  • Supply of metal structures to the facility.
  • Geodetic breakdown of the site.
  • Drilling wells for support stands - 3200 wells.
  • Assembly and installation of metal structures in the design position - 400 pieces.
  • Installation of a security fence of a site of a solar power station.

The entire volume of work was performed by 20 of our specialists with the involvement of 2 units of special machinery, including 2 JCB 4cx backhoe loaders.