In mid-January, the company "BuildService Group" completed construction and installation works at the "Shyroke Solar Park" facility with a capacity of 19.9 MW, a solar power station in Shyroke, Zaporizhia Rayon, Zaporizhia Oblast. Our experts performed the works on an inverter power of 12.55 MW.
We had started to work on the project in October 2018, and already by mid-January of this year, all the works were completed. Our company designed the metal structures for the installation of the photovoltaic modules, performed a geodetic breakdown of the site for the supporting stands for the metal structures, drilled 14854 wells for the supporting stands, assembled, and installed all the 1061 metal structures in the design position.
It should be noticed, that it took 85 calendar days for 40 "BuildService Group" company's specialists to perform the entire volume of the work. Own special machinery was involved, including 1 JCB 4cx backhoe loader, a JCB 155 mini loader, and a tractor for distribution of supporting metal structures for photovoltaic panels