Facility: Construction of an industrial basin
Address: Nova Kahovka
Duration of construction works:
50 calendar days (including work in the winter) from November 5, 2017, till December 12, 2017.
The following works were performed:
- The volume of the work performed on monolithic reinforced concrete 480 m3
The number of staff involved: 10 specialists.